Project Description
Rapid growth and development in the county will require a new fire station to maintain the current level of service to residents. Development and new home construction near Tucker’s Grade or South Gasparilla Rd areas will require the
purchase of property and construction of a new fire station. The location is to be determined based on which area booms first to maintain rapid response time in an area of significant population growth, to minimize loss of life and property damage and perform vital emergency medical services to our citizens.
Project Impacts
Weather
ACOE (Army Corps of Engineers)
Budget
Phase | Cost |
---|---|
Design | $200,000.00 |
Construction | $5,190,000.00 |
Other Costs | $300,000.00 |
Total Budget | $5,690,000.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 11/16/2023 | 02/27/2024 | |
Design Development | 03/01/2024 | 03/01/2025 | |
Construction | 02/01/2024 | 02/01/2026 | |
Turnover & Closeout | 02/01/2026 | 04/01/2026 |
Project Phase
Planning and Project Approval
Last Updated
12/06/2024
Project Manager
Joe Romanelli
Public Relations
Todd Dunn
Email Public Relations
Project Number
c222101
Sponsor Department
Public Safety Charlotte County Fire and EMS
Design Engineer/Architect
Schenkel Shultz
Construction Contractor
Wharton-Smith/Jon F. Swift